GLENVIEW ELEMENTARY SCHOOL, INCREMENT 3

  1. Educational facility construction
  2. Educational facility construction
  3. Educational facility construction
  4. Educational facility construction

Project Type:

Education

Educational facility construction
Educational facility construction
Educational facility construction
Educational facility construction

Location:

Oakland, CA

Owner:

Oakland Unified School District

Project Size:

55,322 square feet

This project included pre-construction services and three separate increments as shown below. It was subject to a Project Labor Agreement, CHPS, 50% local hire goals per trade, and requiresd monthly community meetings to keep the impacted community informed.

Pre-Construction Services | $194,676
Awarded 11/30/14 | Completed 12/10/16

Starting in November 2014, we provided pre-construction services for the demolition and construction of an entire elementary school campus. These services included developing a preliminary project schedule; preparing schematic and design development estimates; providing constructibility reviews; promoting and conducting bid walks for small, local businesses; and generating trade packages for elimination of scope gap.

Increments 1 & 2 | $8,906,000
Awarded 6/8/16 | Completed 11/2017

These increments consisted of abatement and demolition of the existing buildings on campus as well as site preparation and site retaining walls.

Increment 3 | $37,380,043
Awarded 10/11/17 | SC Complete 6/26/20 FC 10/1/20

Our lease-leaseback bid to construct a new school campus in Increment 3 took place on 7/19/17. The GMP was approved by the Board on 10/11/17 after extensive value engineering. Increment 3 itself consisted of construction of a two-story classroom building with AESS Structural Steel and metal framing, a Green HVAC System, Exterior Building Cladding, and includes a library and a basement level.

Self Performed Work:
Rough Carpentry including Blocking, Misc. Finish Carpentry, SWPPP Installation and Maintenance, etc. Challenges: Construction management turnover, neighbor public relations, and unforeseen conditions.

Contact Us

We welcome the opportunity to speak with you about your next project. Contact us today to discuss how we can help you create your finished structure.

Main Office

1141 Marina Way South
Richmond, CA
94804

2nd Location

8055 Collins Drive
Oakland, CA
94621

510.234.4200 phone
510.234.4402 fax

SERVICES

  • Our Services
  • Preconstruction
  • Construction Phase
  • Trades
  • Suppliers
  • Project Handover

Member Log In


© Alten Construction. All Rights Reserved | Contractor #705713

Website Design by Construction Marketing

Sitemap